PORTOS Work Package 6

Each Work Package contains actions with specific and detailed descriptions, deliverables and output results, as well as indicators and expected results.

WP6: Technical viability studies of different marine renewable energies integrated at case-study ports

Start date: 01/03/2020
End date: 30/04/2021
Duration: 14 months

Partner’s Involvement

  • Partner responsible: Fundación Instituto de Hidráulica Ambiental de Cantabria
  • Partners involved:
    • Universidad do Porto
    • Universidad de Santiago de Compostela
    • Ecole D’Ingenieurs En Génie Des Systèmes Industriels
    • Universidad de Oviedo
    • University of Plymouth
    • Instituto de Ciência e Innovaçao en Engenharia Mecânica e Engenharia Industrial
    • Fundación Instituto de Hidráulica Ambiental de Cantabria
    • Administraçao dos Portos do Douro, Leixoes e Viaña do Castelo, SA
    • Autoridad Portuaria de Vigo
    • INNOSEA
    • University College Cork, National University of Ireland, Cork
    • Shannon Foynes Port Company

Action nr.1: Evaluation and optimization of WEC1 pilot technology

Start date: 01/03/2020
End date: 31/10/2020
Duration: 8 months

Results

Action nr.2: Evaluation and optimization of WEC2 pilot technology

Start date: 01/03/2020
End date: 31/10/2020
Duration: 8 months

Results

Action nr.3: Evaluation and optimization of SEC pilot technology

Start date: 01/03/2020
End date: 31/10/2020
Duration: 9 months

Results

Action nr.4: Development of advanced energy storage systems for renewable energy integration

Start date: 01/05/2020
End date: 31/12/2020
Duration: 8 months

Results

Action nr.5: Computation of integrated marine renewable energy production at the target ports

Start date: 01/09/2020
End date: 30/04/2021
Duration: 8 months

Results

Action nr.6: Potential of other harvestable renewable energy resource at the case-study ports

Start date: 01/09/2020
End date: 30/04/2021
Duration: 8 months

Results