Each Work Package contains actions with specific and detailed descriptions, deliverables and output results, as well as indicators and expected results.
WP6: Technical viability studies of different marine renewable energies integrated at case-study ports
Start date: 01/03/2020
End date: 30/04/2021
Duration: 14 months
Partner’s Involvement
- Partner responsible: Fundación Instituto de Hidráulica Ambiental de Cantabria
- Partners involved:
- Universidad do Porto
- Universidad de Santiago de Compostela
- Ecole D’Ingenieurs En Génie Des Systèmes Industriels
- Universidad de Oviedo
- University of Plymouth
- Instituto de Ciência e Innovaçao en Engenharia Mecânica e Engenharia Industrial
- Fundación Instituto de Hidráulica Ambiental de Cantabria
- Administraçao dos Portos do Douro, Leixoes e Viaña do Castelo, SA
- Autoridad Portuaria de Vigo
- INNOSEA
- University College Cork, National University of Ireland, Cork
- Shannon Foynes Port Company
Action nr.1: Evaluation and optimization of WEC1 pilot technology
Start date: 01/03/2020
End date: 31/10/2020
Duration: 8 months
Results
Action nr.2: Evaluation and optimization of WEC2 pilot technology
Start date: 01/03/2020
End date: 31/10/2020
Duration: 8 months
Results
Action nr.3: Evaluation and optimization of SEC pilot technology
Start date: 01/03/2020
End date: 31/10/2020
Duration: 9 months
Results
Action nr.4: Development of advanced energy storage systems for renewable energy integration
Start date: 01/05/2020
End date: 31/12/2020
Duration: 8 months
Results
Action nr.5: Computation of integrated marine renewable energy production at the target ports
Start date: 01/09/2020
End date: 30/04/2021
Duration: 8 months
Results
Action nr.6: Potential of other harvestable renewable energy resource at the case-study ports
Start date: 01/09/2020
End date: 30/04/2021
Duration: 8 months